Layout: Strings, Batter Boards, and Square Corners
Good concrete starts with accurate layout. Your goal is to transfer the plan (shape, width, and location) onto the ground so the forms can be set quickly and checked easily. The most reliable approach for small projects is a string layout supported by batter boards so strings can be adjusted without moving stakes in the excavation area.
Using batter boards and stringlines
Batter boards are temporary boards fastened to stakes outside the slab area. They hold stringlines at a consistent height and allow fine adjustments. Place them far enough away that they won’t be disturbed by digging, base placement, or form installation.
- Step 1: Establish a reference line. Pick one straight edge of the project (often the longest side) and set two batter-board assemblies beyond each end.
- Step 2: Stretch a stringline between batter boards. Pull it tight; a sagging string creates layout errors. If the span is long, add intermediate batter boards to support the string.
- Step 3: Mark the string position on the batter boards. Use pencil marks or small nails/screws so you can remove and re-tension the string without losing the location.
- Step 4: Create parallel lines for slab width. Measure perpendicular offsets from the first string to set the opposite edge string. Use a tape measure at multiple points to confirm the offset is consistent.
Squaring corners: diagonals and the 3-4-5 method
Square corners prevent tapering slabs, crooked walkways, and forms that fight each other. Two common checks are diagonal measurements and the 3-4-5 triangle.
- Diagonal check (rectangles/squares): Measure corner-to-corner diagonals. When both diagonals match, the layout is square. Adjust by shifting one stringline slightly on the batter boards until the diagonals are equal.
- 3-4-5 method (right angle setup): From a corner point on your baseline string, measure 3 units along the baseline and mark. From the same corner, measure 4 units along the perpendicular direction and mark. The distance between those two marks should be 5 units. Scale up for accuracy (6-8-10, 9-12-15, etc.).
Control points: marking corners, edges, and key offsets
Strings show lines, but you also need physical reference points that survive bumps and wind. Create control points that let you re-check location and grade at any time.
- Corner plumb marks: Drop a plumb bob from string intersections and mark the ground with paint or a nail/spike.
- Offset marks: Mark a second set of points a fixed distance outside the slab edge (for example, 12 in. offset). If a form gets moved, you can re-measure from the offset points to restore position.
- Grade control marks: Mark stakes with “top of form” or “finished surface” elevations so everyone is working to the same target.
Establishing Finished Elevation and Slope
Layout is not just left-right; it’s also up-down. You need a clear reference for finished elevation (where the concrete surface ends up) and slope (how it drains). A small error in grade can cause standing water or a slab that is too thin at one edge.
- Listen to the audio with the screen off.
- Earn a certificate upon completion.
- Over 5000 courses for you to explore!
Download the app
Pick a benchmark and define targets
A benchmark is a fixed reference elevation you can return to (top of a driveway, a marked stake, a masonry step). From the benchmark, you set the target elevation for the finished surface and then derive the top-of-form elevation.
- Finished surface elevation (FSE): The intended top of concrete.
- Top of form (TOF): Usually equals FSE for slabs and flatwork, because you strike off to the form tops.
- Bottom of slab elevation: FSE minus slab thickness (and minus thickened-edge depth where applicable).
Tools for grade: line level, laser level, and water level
Any of these can work well; choose based on budget, site conditions, and required accuracy.
- Line level: A small level that hangs on a string. Best for short runs and quick checks. Keep the string tight and avoid wind.
- Laser level: Fast and accurate for longer distances or multiple points. A rotary laser with a grade rod makes it easy to set many stakes to the same elevation.
- Water level: A clear hose filled with water. Extremely accurate over distance and around obstacles because water seeks the same level at both ends. Great when line-of-sight is blocked.
Setting slope (drainage) in practical terms
Slope is often expressed as “drop per foot.” A common exterior flatwork slope is about 1/8 in. per ft to 1/4 in. per ft away from structures, but always follow local requirements and the needs of the site.
Example: A 10 ft walkway sloping at 1/8 in. per ft needs a total drop of 10 × 1/8 in. = 1-1/4 in.. If the high end TOF is 100.00 (your chosen reference), the low end TOF should be 98.75 if you’re working in quarter-inch increments, or simply mark it as “1-1/4 in. lower than high end” on your stakes.
Step-by-step: setting TOF marks with a laser (similar logic for water level)
- Step 1: Set the laser on stable ground where it can “see” all form lines.
- Step 2: Take a reading at the benchmark and record it (this ties the laser plane to your project).
- Step 3: Calculate the desired TOF at key points (corners, ends, and any grade breaks).
- Step 4: Use the grade rod to find the rod reading that corresponds to each TOF. Mark stakes or batter boards with a clear line labeled
TOF. - Step 5: Snap or stretch strings at TOF height if helpful, or use the marks to set the forms directly.
Form Building for Straight Work: Materials, Stakes, Fastening, and Bracing
Forms are temporary molds that must hold shape under the pressure of wet concrete and the vibration/rodding used during placement. Straight forms should be straight, stiff, and well supported so the slab edge is clean and the top edge is a reliable screed guide.
Lumber and form material choices
- Common lumber: Straight 2x4s are typical for 3-1/2 in. slabs; 2x6s are common for 5-1/2 in. slabs or where you want a taller form for thickened edges.
- Engineered/metal forms: Reusable and very straight, but may be less convenient for one-off small projects.
- Quality matters: Pick boards that are straight, not twisted, and not badly crowned. Sight down the board length before buying/using.
Setting forms to account for slab thickness, base thickness, and thickened edges
Forms define the slab perimeter and TOF, but you must also ensure the excavation and base allow the correct concrete thickness everywhere.
- Standard slab thickness: Set TOF first, then confirm the bottom of slab elevation by measuring down from TOF at multiple points.
- Base thickness allowance: Your base should end at the correct elevation so that when concrete is placed, the slab thickness is consistent. Use a story pole (a marked stick) to quickly check depths.
- Thickened edges/footings: If the slab edge needs to be thicker, the form top may stay the same, but the excavation below the edge must be deeper/wider. Mark thickened-edge zones on the ground and verify depth before forming or before final checks.
Stake spacing and placement
Stakes keep forms from moving outward (blowouts) or inward (pinching). Spacing depends on pour height, soil support, and how straight you need the edge.
- Typical spacing: About 2–4 ft apart for small flatwork forms, closer at corners, ends, and where the ground is soft.
- Stake position: Drive stakes on the outside of the form so the inside face stays clean. Keep stake tops below TOF so they don’t interfere with screeding.
- Preload the form: Push the form against the stringline and stake it there; don’t “pull it into place” with fasteners alone.
Fastening methods (and why they matter)
- Screws: Great for adjustability and removal. Use exterior/deck screws. Pre-drill near board ends to reduce splitting.
- Nails: Fast and strong, but harder to adjust. Duplex nails are easier to pull.
- Form clamps/hardware: Useful for reusable systems or where you need quick alignment.
Fasten the form to stakes so the form top stays at TOF and the form face stays on the layout line. Check alignment after each fastening step; forms often creep as you tighten fasteners.
Bracing corners and joints
Corners are high-stress points where concrete pressure and worker traffic can rack the form out of square.
- Corner blocks: Add a short 2x piece across the outside of the corner joint to stiffen it.
- Diagonal braces: Stake a diagonal brace from the form to the ground to prevent the corner from opening during the pour.
- Splice plates: Where two form boards join end-to-end, use a scab (short board) across the joint on the outside to keep the form straight.
Preventing blowouts (forms spreading or failing)
Blowouts usually happen because of weak stakes, wide stake spacing, poor fastening, or unbraced joints—especially when concrete is placed quickly or vibrated aggressively.
- Increase stake density near corners, curves, and any tall/thickened sections.
- Add kickers (angled braces) to resist outward pressure.
- Keep joints tight and reinforce splices.
- Place concrete evenly along the form rather than piling it in one spot (this reduces localized pressure).
Curved Forms: Flexible Materials, Layout, Staking, and Bracing
Curves require a different mindset: instead of forcing a straight board to bend (which creates kinks), use flexible facing materials and more frequent stakes to hold a smooth radius.
Layout for curves: control points and offsets
- Mark the curve centerline or edge: Use paint to draw the intended curve on the ground.
- Set control points: Mark key points along the curve (start, end, and intermediate points every 1–2 ft). These points let you check the form position as you bend it.
- Use offsets for consistent width: For a curved walkway, measure a fixed offset from the first curve to mark the second edge, checking at many points to avoid width drift.
Flexible form materials
- Thin plywood strips: Common and strong. Rip plywood into strips (for example, 6–8 in. tall) so it bends smoothly. Thinner strips bend tighter.
- Hardboard (tempered): Bends well for gentle curves and leaves a smooth edge but can be less durable if over-wet or over-fastened.
- Plastic/composite bender board: Designed for curves; convenient but needs good staking to prevent waviness.
Step-by-step: building a smooth curved form
- Step 1: Pre-set stakes along the curve. Place stakes on the outside of the curve at close spacing (often 12–24 in. apart depending on radius and form stiffness).
- Step 2: Attach the flexible form gradually. Start at one end, fasten to the first stake, then bend to the next stake and fasten, working your way along. This reduces kinks.
- Step 3: Check the curve against control points. Measure from reference marks or use a template/string arc if you have a defined radius.
- Step 4: Set TOF and brace. Curves tend to “roll” (top edge tilts). Add braces or blocks to keep the form plumb and the top edge at grade.
- Step 5: Build the opposite curve. Use spacers cut to the walkway width to maintain consistent distance between forms along the curve.
Bracing curves to prevent waviness
Curved forms can look fine until concrete pressure reveals weak spots. The fix is more support, not more force.
- More stakes, closer together is the primary solution.
- Walers (stiffening rails): Fasten a straight 2x along the outside of the flexible form (where possible) to smooth minor waves.
- Kickers: Add angled braces at intervals to resist outward pressure, especially on the outside of tight curves.
Form Release, Sealing, and Edge Quality
Release agents: when and how to use them
A light coat of form release helps forms strip cleanly and reduces surface tearing. Use a product intended for concrete forms or a light application of suitable release oil. Avoid over-application; excess can stain concrete or interfere with finishes.
- Apply after forms are set and checked so you don’t disturb alignment.
- Keep release off reinforcement and base where it could create bond issues at edges.
Sealing forms to prevent paste loss
Gaps under or between forms allow cement paste to leak out, leaving honeycombing and weak, rough edges.
- Seal small gaps: Use foam backer rod, weatherstrip, or a thin bead of caulk along the inside bottom edge where needed.
- Pack soil at the outside base: Lightly backfill and tamp against the outside of the form to support it and reduce leakage paths (without pushing the form out of line).
- Check joints: Tighten splices and add scab plates so joints don’t open during placement.
Checking Alignment and Grade: A Pre-Pour Inspection Routine
Before concrete arrives, do a systematic walk-through. The goal is to catch problems while they are still easy to fix.
Pre-pour checklist (use it in order)
- 1) Layout verification: Confirm the form inside edges match the stringlines or control points. Re-check key dimensions (lengths, widths, offsets).
- 2) Square check: Measure diagonals again for rectangular work. For curves, re-check width at many stations using spacers or tape.
- 3) Straightness/smoothness: Sight along straight forms; for curves, look for flat spots or kinks and add stakes where needed.
- 4) Plumb and stability: Push on forms by hand. If anything moves, add stakes, screws, or kickers. Confirm corners and splices are braced.
- 5) Top-of-form grade: Use your level method (laser/water/line) to verify TOF at corners and intermediate points. Mark any high/low spots and adjust now.
- 6) Thickness confirmation: Measure down from TOF to the base at multiple points to confirm slab thickness. Verify any thickened-edge excavations are in the right locations and depths.
- 7) Sealing and release: Confirm gaps are sealed where needed and release agent is applied lightly and evenly.
- 8) Clearance and access: Ensure there is room for wheelbarrows/chutes, and that stakes/braces won’t interfere with screeding and finishing paths.
Quick field tips for adjustments
| Problem found | Likely cause | Fast fix before the pour |
|---|---|---|
| Form edge wanders off line | Stakes too far apart; board crown | Add stakes; re-fastening while holding to string; flip or replace crowned board |
| Top of form dips | Weak stake support; uneven ground under stake | Add a stake; shim under form; re-drive stake; add kicker |
| Corner opens when pushed | Insufficient corner bracing | Add corner block and diagonal brace; add stake close to corner |
| Visible gaps under form | Uneven ground; form not seated | Pack soil outside; seal inside edge; re-set form section |
| Curved form has kinks | Stakes too far apart; material too stiff | Add stakes between; switch to thinner strip; re-attach gradually |