Reinforcement Basics: Rebar, Wire Mesh, and Proper Placement

Capítulo 4

Estimated reading time: 12 minutes

+ Exercise

What Reinforcement Does (and Does Not Do)

Concrete is strong in compression but weak in tension. As a slab shrinks while curing, changes temperature, or settles slightly, it develops tensile stresses and cracks. Reinforcement’s main job in small flatwork is to control crack width and hold cracked sections tightly together so the slab behaves as a single unit under service loads.

  • Reinforcement does not “stop cracks.” Even well-reinforced slabs can crack; the goal is smaller, tighter cracks that don’t open, curl, or fault as easily.
  • Reinforcement is not a substitute for joints. Control joints still do the primary work of “telling” the slab where to crack.
  • Reinforcement does not fix poor support. If the slab loses support (voids, pumping, erosion), steel can’t prevent settlement-related cracking.

Common Reinforcement Options for Small Projects

1) Welded Wire Mesh (WWM)

What it is: A factory-welded grid of wires (often sold in rolls or sheets). Typical small-project mesh might be labeled by wire size and spacing (for example, 6x6 W1.4/W1.4), meaning 6 in. spacing each way with a certain wire cross-section.

  • Best for: Light-duty slabs and walkways where you want crack control with minimal layout time.
  • Pros: Fast coverage, consistent spacing, good for shrinkage crack control when placed correctly.
  • Cons: Commonly installed wrong (left on the ground). Rolls tend to “spring” and are hard to keep flat. Thin wire can be less forgiving if it ends up too low.

2) Rebar Grid (Deformed Bars)

What it is: Individual steel bars (e.g., #3, #4) placed in a grid pattern and tied at intersections.

  • Best for: Pads with heavier loads (trash enclosure pad, shed slab, small driveway apron), slabs with thickened edges, areas with concentrated loads, or where you need targeted extra steel near corners/penetrations.
  • Pros: Easier to keep at the correct height using chairs/bolsters; easy to add extra bars where needed; robust.
  • Cons: More cutting/tying; can be overbuilt or poorly detailed (wrong cover, poor laps).

3) Fiber Reinforcement (Microfibers/Macrofibers)

What it is: Fibers mixed into the concrete at the batch plant or added to the mixer. Microfibers mainly reduce plastic shrinkage cracking; some macrofibers can contribute to post-crack toughness depending on product and dosage.

  • Best for: Reducing early-age surface cracking (plastic shrinkage) and improving toughness in some slabs when specified.
  • Pros: No placement labor; helps with early microcracks; nothing to “sink” or get stepped on.
  • Cons: Not a direct replacement for steel in many flatwork situations; finishing can feel “hairy” if overworked; performance depends heavily on correct dosage and mix design.

4) Combining Systems (Common in Practice)

  • Fiber + rebar/mesh: Fibers help early-age cracking; steel controls crack width long-term.
  • Mesh + rebar at edges/openings: Mesh for general crack control, with extra bars where stress concentrates.

Practical Sizing and Spacing Concepts (Without Over-Engineering)

For small slabs, reinforcement selection is usually driven by: slab thickness, expected loads, joint spacing, and “problem areas” (corners, re-entrant corners, penetrations, transitions).

Continue in our app.

You can listen to the audiobook with the screen off, receive a free certificate for this course, and also have access to 5,000 other free online courses.

Or continue reading below...
Download App

Download the app

Bar Size Basics

  • #3 rebar is 3/8 in. diameter (common for walkways and light pads).
  • #4 rebar is 1/2 in. diameter (common for heavier pads, thickened edges, or where you want more stiffness).

In practical terms: if you can bend it slightly by hand, it’s probably too small for structural help; if it’s hard to cut and stays straight, it’s usually robust enough for typical flatwork crack control when properly placed.

Spacing Basics

Think of spacing as “how far a crack can travel before it gets stitched.” Tighter spacing generally means better crack control, but costs more and can be harder to place.

  • Typical light flatwork: A grid around 12–18 in. on center each way is common for small pads/walkways when using rebar.
  • Heavier or more crack-sensitive areas: 8–12 in. on center each way is common where loads are higher or geometry is tricky.

For welded wire mesh, the spacing is built into the sheet/roll (often 6x6 in. or 4x4 in.). The key is not the spacing alone—it’s the height in the slab.

Edge Conditions and Transitions (Where Problems Start)

  • Free edges (slab edges not restrained by another slab): Edges are prone to curling and cracking. Consider a perimeter bar (or thickened edge with bars) to help hold the edge together.
  • Thickened edges/grade beams: If your slab thickens at the perimeter, place bars in the thickened section per plan; keep proper cover from soil and forms.
  • Transitions (new slab meets old slab, slab meets footing, slab meets asphalt): Expect differential movement. Use isolation material where required; if dowels are used, align them carefully and keep them at mid-depth of the slab section they’re intended to support.
  • Re-entrant corners: Inside corners (like an “L” shape) concentrate stress and crack easily. Add diagonal bars (“corner bars”) to distribute stress.

Correct Placement: Height, Support, and Cover

The Most Common Failure: Reinforcement on the Ground

If mesh or rebar sits on the subgrade, it does very little for crack control because cracks typically open from the top as the slab shrinks and curls. Reinforcement must be positioned where it can resist tension from service conditions.

  • Rule of thumb for slabs-on-grade: Place reinforcement around the middle to upper third of the slab thickness for crack control (unless a design calls for something else).
  • For welded wire mesh: It must be supported and kept up—not rolled out and buried.

Cover: Keeping Steel Away from Soil and Surfaces

Cover is the concrete thickness protecting steel from moisture and corrosion and preventing steel from printing through the surface.

  • Bottom cover over soil: Keep steel lifted off the ground. A practical target is about 2 in. of concrete between steel and soil for slabs-on-ground unless your local requirements differ.
  • Top cover: Keep steel far enough below the surface to avoid rust staining and spalling. A practical minimum is often around 1 1/2–2 in. below the finished surface for small flatwork, adjusted for slab thickness and bar size.
  • Side cover at forms: Don’t let bars touch forms. Maintain roughly 2 in. from slab edges when exposed to weather/soil.

Practical check: after you set chairs, measure from the form top down to the steel and compare to slab thickness. If the steel is too low, it’s “decorative.” If it’s too high, it can telegraph and cause surface issues.

Supports: Chairs, Bolsters, and Dobies

  • Chairs (plastic or metal): Used to hold rebar or mesh at a set height. Choose a chair height that puts steel in the intended zone (middle/upper third) while maintaining bottom cover.
  • Bolsters (continuous supports): Great under mesh or long bars to prevent sagging between chairs, especially on soft subgrade.
  • Dobies (concrete blocks): Common on some jobs; use only clean, purpose-made dobies that won’t crumble. Place them stable-side down. Avoid random bricks/rocks (they shift and can create voids).

Spacing supports: closer spacing prevents “hammocking” (steel sagging between supports). If you can step near the steel and it drops noticeably, add more supports or switch to bolsters.

Keeping Mesh in the Right Zone

Mesh tends to end up at the bottom because workers walk on it during the pour. Use these tactics:

  • Pre-support the mesh on chairs/bolsters before the pour.
  • Use manageable sheet sizes when possible instead of springy rolls.
  • During placement, lift-and-set correctly: If you must adjust mesh while pouring, lift it with a hook and set it back onto supports—don’t just “pull it up” and let it fall.
  • Watch overlaps: Overlapped mesh creates a stiffer ridge that can end up too high unless supported evenly.

Tying Basics: Secure, Not Over-Tight

Tie Wire and Tools

  • Common tie wire: 16-gauge is widely used for small rebar; 18-gauge can work for light tying but is easier to break.
  • Tools: Tie wire reel, nippers/pliers, or a tying tool (manual or automatic). Cut ends should be bent down away from the surface and away from where hands will be during finishing.

Common Tie Types (Practical Use)

  • Snap tie (simple wrap): Fast for most slab grids; adequate when bars are well supported.
  • Saddle tie: Helpful when one bar sits on top of another and you want it to stay seated.
  • Figure-8 tie: More secure for intersections that want to shift (like at edges or where workers will step).

Goal: keep intersections from shifting during concrete placement. You are not building a suspension bridge—over-tying wastes time and can make it harder to adjust alignment.

Avoiding Over-Tying

  • Don’t tie every intersection unless needed. A common approach is tying every other intersection, then adding ties at edges, laps, and around openings where movement is likely.
  • Don’t crank ties so tight that wire snaps or twists bars out of alignment.

Lap Splices and Overlaps

Rebar Lap Splices

When one bar must continue past its length, overlap it with the next bar. For small projects without engineered drawings, a conservative practical lap is:

  • Lap length: About 40 bar diameters (a common field rule). That’s roughly 15 in. for #3 (0.375 in. dia) and 20 in. for #4 (0.5 in. dia).

Place laps so they don’t all occur in the same line (stagger them) when possible, and keep laps supported so they don’t sink.

Wire Mesh Overlaps

  • Overlap at least one full grid spacing (often 6 in. or more), and more if the mesh is light.
  • Tie overlaps so sheets don’t separate when concrete is placed.

Keeping Reinforcement from Moving During the Pour

  • Use enough supports: Chairs/bolsters/dobies placed so steel stays at height even when workers step nearby.
  • Create “walk paths”: Use kneeboards or temporary planks where practical so workers aren’t stepping directly on the grid.
  • Pre-plan penetrations: Frame around pipes/sleeves so the grid doesn’t get cut and left unsupported.
  • Check before placing concrete: Walk the forms and physically push the grid—if it rocks, add ties/supports.

Where to Add Extra Reinforcement (Corners, Re-Entrant Corners, Penetrations)

Outside Corners

Outside corners can chip and crack. Add a perimeter bar near the edge or return bars that wrap the corner in the grid pattern. Keep proper side cover so steel isn’t too close to the edge.

Re-Entrant Corners (Inside Corners)

These are crack starters. Add diagonal bars at about 45 degrees across the corner, placed in the same elevation as the main reinforcement.

  • Practical detail: Two diagonal #3 bars, 24–36 in. long, centered across the inside corner, often helps for small slabs (adjust to slab size and loads).

Around Penetrations (Pipes, Posts, Drains)

Any hole or sleeve interrupts the slab and concentrates stress.

  • Box-out strategy: Keep the main grid continuous when possible by placing bars around the opening (a “picture frame” of bars) and add short diagonal bars at corners of square openings.
  • Maintain cover: Don’t let steel crowd the penetration so tightly that concrete can’t consolidate around it.

Step-by-Step Reinforcement Checklist: Typical Walkway

Scenario

Residential walkway, light foot traffic, typical thickness (often around 4 in.), straight run with a few turns.

Checklist

  1. Choose reinforcement approach: Use welded wire mesh for general crack control, or #3 rebar grid if you want easier height control and better detailing at corners/turns.
  2. Plan joint layout first: Reinforcement supports crack control, but joints control crack location. Ensure reinforcement won’t interfere with planned joint tooling/sawing.
  3. Lay out the grid:
    • For rebar: mark spacing on forms (e.g., 12–18 in. o.c.).
    • For mesh: pre-cut sheets to fit, minimizing excessive overlaps.
  4. Set supports:
    • Place chairs/bolsters so steel lands in the middle/upper third while maintaining bottom cover.
    • Add extra supports at overlaps and where workers will step.
  5. Install reinforcement:
    • Keep steel back from forms to maintain side cover.
    • Overlap mesh and tie overlaps.
    • For rebar, tie intersections as needed (every other intersection plus edges/laps).
  6. Detail corners and turns:
    • Add diagonal bars at re-entrant corners (inside turns).
    • Ensure perimeter bars (if used) maintain cover at edges.
  7. Final pre-pour check:
    • Measure height to confirm steel is not on the ground.
    • Push-test for wobble; add ties/supports where movement is likely.
    • Confirm no sharp tie-wire ends point upward toward the finish surface.

Step-by-Step Reinforcement Checklist: Typical Pad (Shed/Equipment/Trash Cans)

Scenario

Small pad with occasional heavier point loads (wheels, jack stands, stored materials), possibly with a thickened edge or a doorway threshold area.

Checklist

  1. Select reinforcement:
    • Common choice: #3 or #4 rebar grid (often 12 in. o.c. for more robust crack control).
    • Consider fiber as an add-on for early crack reduction, not as the only reinforcement if you expect heavier use.
  2. Plan transitions and penetrations:
    • Mark any posts, anchors, sleeves, or drains.
    • Decide where you need “picture frame” bars around openings.
  3. Lay out and cut bars:
    • Keep bars continuous where possible; plan lap splices (about 15 in. for #3, 20 in. for #4 as a conservative field rule).
    • Stagger laps so they don’t line up in one weak band.
  4. Support the grid:
    • Use chairs/bolsters sized to maintain bottom cover from soil and keep steel in the intended zone.
    • Add extra supports under laps and where bars cross thickened sections.
  5. Tie efficiently:
    • Tie intersections enough to prevent shifting during placement.
    • Use stronger ties (figure-8) at edges, laps, and around penetrations.
  6. Add extra steel at stress points:
    • Re-entrant corners: add diagonal bars.
    • Square openings: add diagonal bars at corners of the opening and a bar “frame” around it.
    • Edges prone to loading: consider a perimeter bar set back to maintain cover.
  7. Pre-pour stability check:
    • Verify cover at sides and bottom.
    • Confirm reinforcement won’t be pushed down by the first concrete placement—add bolsters if needed.
    • Ensure reinforcement won’t interfere with any planned jointing or embedded items.

Quick Reference Table: Placement Targets (Field-Friendly)

ItemCommon GoalCommon MistakeField Fix
Wire meshMiddle/upper third of slabLeft on groundChairs/bolsters; lift-and-set onto supports during pour
Rebar gridConsistent height, proper coverToo close to edge/formsReposition and add chairs; measure cover before pour
Lap splicesLong enough overlap, supportedShort laps or all laps in one lineUse ~40 diameters; stagger laps; tie and support
PenetrationsReinforcement continuity around openingCut bars and leave gapAdd frame bars and diagonals; keep cover and consolidation space

Now answer the exercise about the content:

Why should welded wire mesh or rebar be supported in the middle to upper third of a slab instead of left on the subgrade?

You are right! Congratulations, now go to the next page

You missed! Try again.

In slabs-on-grade, cracks typically open from the top during shrinkage and curling. If steel sits on the ground, it does little. Keeping reinforcement in the middle/upper third helps it control crack width and keep cracked sections tight.

Next chapter