Why Moisture Ruins Epoxy Floors

Epoxy bonds best to concrete that is dry enough and stable enough to stay that way. When moisture is present in or under a slab, it can interfere with adhesion and curing, and it can physically push the coating off the surface. The most common moisture-driven failures are blistering, bubbles (pinholes or domes), whitening/hazing (sometimes called “blush” or cloudiness), and delamination (peeling or sheets releasing).

What actually happens under an epoxy film

  • Blistering: Water vapor accumulates under the coating and forms a pocket. As vapor pressure builds, the pocket grows into a blister. If the coating is still soft, the blister may look like a bubble; if cured, it may feel like a raised dome.
  • Bubbles and pinholes: Moisture can carry air and dissolved gases through pores and capillaries. As the coating warms or cures, vapor expands and escapes through the wet film, leaving craters or pinholes.
  • Delamination: Moisture at the interface reduces adhesion and can create a weak boundary layer. Pressure cycles (wet/dry, warm/cool) repeatedly stress the bond until the coating releases.

How Moisture Moves Through Concrete Slabs

Concrete is not waterproof. It contains a network of capillaries and pores that allow moisture to move. Even when the surface looks dry, moisture can be migrating upward from deeper in the slab or from the soil below.

Three beginner-friendly movement paths

  • Capillary rise: Moisture wicks upward through tiny pores, similar to how a paper towel draws water.
  • Vapor diffusion: Water changes to vapor and moves from areas of higher vapor pressure to lower vapor pressure.
  • Liquid water intrusion: Cracks, joints, or missing/failed under-slab vapor barriers can allow liquid water to enter and then evaporate upward.

Key concepts you will hear in product data sheets

Hydrostatic pressure: This is pressure from liquid water. In flooring, it usually means water is being forced through the slab due to a high water table, poor drainage, or water trapped under the slab. True hydrostatic pressure can overwhelm many coatings and is often a building/drainage issue, not just a coating issue.

Vapor drive: This is the “push” of water vapor moving from wet to dry areas. If the bottom of the slab is wetter than the top (common), vapor drive is upward. A coating can act like a lid, trapping vapor and increasing pressure at the bond line.

Dew point: Dew point is the temperature at which air becomes saturated and water condenses. If the slab surface is at or below the dew point, moisture can form on the surface even if the slab is otherwise acceptable. That thin film of condensation can cause adhesion loss, amine blush, or cloudy finishes.

Continue in our app.

You can listen to the audiobook with the screen off, receive a free certificate for this course, and also have access to 5,000 other free online courses.

Or continue reading below...
Download App

Download the app

ConceptWhat you see on the jobWhy it matters
Hydrostatic pressurePersistent wetness, water seepage, damp cracks/jointsMay require drainage fixes; coatings alone may fail
Vapor driveSurface seems dry but coatings blister laterRequires moisture testing and possibly mitigation primers
Dew pointCoating looks milky, fisheyes, poor adhesion in spotsControl temperature/humidity; avoid coating on “sweating” slabs

Moisture Screening: Plastic Sheet Test (Preliminary Indicator)

The plastic sheet test is a quick screening tool. It does not quantify vapor emission, but it can warn you that moisture is active and that professional testing or mitigation is likely needed.

Step-by-step plastic sheet test

  1. Choose locations: Pick at least 3 areas: one near an exterior wall, one near a door, and one in the center. Add more if the slab is large or has known damp areas.
  2. Prep the spot: Sweep and vacuum. The surface should be free of standing water and loose dust. Do not wash the area right before the test.
  3. Cut plastic: Use clear polyethylene sheet (commonly 6 mil). Cut squares about 18 in x 18 in (or larger).
  4. Seal edges: Tape all four edges tightly to the concrete with a moisture-resistant tape, creating an airtight seal. Press firmly so there are no gaps.
  5. Wait: Leave in place 24–48 hours (longer can be more revealing if conditions are stable).
  6. Inspect: Look for condensation on the underside of the plastic and darkening of the concrete.

How to interpret what you see

  • Condensation droplets under plastic: Strong sign of active moisture vapor movement. Plan on professional testing and/or a moisture-mitigation system.
  • Concrete darkens but no droplets: Moisture may still be present (especially in humid conditions). Treat as a caution flag and proceed to professional testing if you plan a non-breathable coating.
  • No change: Encouraging, but not proof. You can still have elevated internal RH that will affect epoxy long-term.

Common mistake: Running the plastic test right after rain, washing, or heavy mopping can create false positives. If the building is not climate-controlled, daily humidity swings can also confuse results.

Professional Moisture Tests: What They Measure and What Results Mean

When you need numbers to match a coating system’s limits, use professional methods. Always compare results to the specific product data sheet (PDS) for the primer, body coat, and topcoat you plan to use.

Calcium Chloride Test (MVER)

This test estimates Moisture Vapor Emission Rate (MVER) from the slab surface, typically reported as lb/1000 ft²/24 hr. It is a surface-based test and is sensitive to ambient conditions.

  • What it tells you: How much moisture vapor is leaving the slab surface under the test dome during the test period.
  • Typical coating implications (general guidance): Many standard epoxies are often specified for lower MVER values; higher values usually push you toward moisture-mitigation primers or vapor barrier epoxies.
  • Limitations: Not ideal for lightweight concrete or slabs with certain surface treatments; can vary with HVAC conditions and surface prep state.

In-Situ Relative Humidity (RH) Testing

In-situ RH testing measures internal moisture condition by placing probes in drilled holes at a specified depth (commonly a percentage of slab thickness depending on whether the slab dries from one side or two). Results are reported as %RH.

  • What it tells you: How much moisture is present inside the slab, which is often a better predictor of long-term moisture behavior after you “cap” the slab with epoxy.
  • Typical coating implications (general guidance): Lower internal RH is compatible with more coating options; higher RH often requires a moisture-mitigation primer system designed for elevated RH.
  • Limitations: Requires proper installation, equilibration time, and following the test standard and probe manufacturer instructions.

How to use test results for coating selection (beginner workflow)

  1. Collect requirements: Find the moisture limits in the PDS for each layer (primer, build coat, topcoat). Do not assume all epoxies have the same limits.
  2. Match the strictest layer: The system is only as tolerant as its least-tolerant component (often the primer or the bond line).
  3. Decide on a path:
    • If results are within limits, proceed with the specified system.
    • If results are near the limit, consider a more moisture-tolerant primer to add safety margin.
    • If results are above limits, select a tested moisture-mitigation system (vapor barrier epoxy or moisture-tolerant primer system) or address site drainage/under-slab issues.
  4. Document conditions: Record ambient temperature, RH, and slab temperature (dew point risk). Keep test reports with the job file.

Important: “Typical” acceptable numbers vary widely by manufacturer and product line. Treat any rule-of-thumb thresholds as a starting point only; the PDS and technical support guidance are the decision authority.

Recognizing Moisture-Related Symptoms vs Other Failures

Many coating problems look similar at first glance. Use symptom patterns and simple checks to avoid misdiagnosing a moisture issue as a mixing or application mistake.

Moisture-related red flags

  • Blisters that appear days to months later, especially after rain, seasonal humidity changes, or HVAC shutdowns.
  • Blisters concentrated near exterior walls, below grade areas, around floor drains, or along cracks/joints.
  • White haze or cloudy areas that correlate with cool slab temperatures or high humidity (dew point risk).
  • Delamination with damp underside: When a blister is cut open, the concrete under it may look darker or feel damp.

Symptoms more often caused by non-moisture issues (quick contrasts)

  • Uniform pinholes everywhere: Often linked to outgassing from warming concrete, roller technique, or coating viscosity; moisture can contribute but is not the only cause.
  • Soft or tacky coating: Commonly mix ratio errors, poor mixing, low temperatures, or expired material (though moisture can also interfere with cure in some chemistries).
  • Fish-eyes/craters: Frequently contamination (silicones, oils) rather than slab moisture.

Field check: blister “autopsy” (simple and informative)

  1. Cut an “X” into a blister with a sharp blade.
  2. Peel back the flaps and inspect the underside of the coating and the concrete surface.
  3. Look for moisture darkening, salts/efflorescence (white crystalline residue), or a clean separation line at the concrete interface.
  4. Smell is not a reliable indicator, but visible dampness and salts strongly suggest moisture movement.

Note: Efflorescence indicates water movement through concrete carrying soluble salts. Even if the surface looks dry later, the movement can continue and stress coatings.

Mitigation Options When Moisture Is Too High

If moisture testing or symptoms indicate elevated vapor emission or high internal RH, you generally have two categories of options: reduce the moisture source/drive, or use a coating system designed to tolerate it.

Option A: Reduce the moisture source (building-side fixes)

  • Improve exterior drainage and grading; extend downspouts away from the slab.
  • Repair plumbing leaks, irrigation overspray, or interior water sources.
  • Evaluate whether the slab lacks an effective under-slab vapor retarder (common in older construction). This may require professional assessment.

When there is true hydrostatic pressure (liquid water being forced through), coatings alone are often unreliable. Addressing drainage and water management becomes the priority.

Option B: Use moisture-tolerant primers and vapor barrier epoxies

Moisture mitigation systems are typically epoxy primers formulated and tested to handle higher MVER and/or higher in-situ RH. They are installed as a continuous, properly thick layer to reduce vapor transmission into the coating system.

  • Moisture-tolerant primer: Used when moisture is elevated but within the primer’s published limits. Often applied before the main epoxy build coat.
  • Vapor barrier epoxy (moisture mitigation epoxy): A more robust system designed to block or greatly reduce vapor transmission. Often requires strict film thickness targets and sometimes broadcast sand for mechanical bond to subsequent layers.

Practical selection checklist (what to verify before you buy)

  • Published limits: Confirm the product’s maximum allowable MVER and/or %RH in the PDS.
  • Required thickness: Many mitigation epoxies only work when installed at the specified mil thickness. Verify coverage rate and plan material quantity accordingly.
  • Surface profile requirements: Mitigation primers still require proper mechanical profile; check the PDS for required CSP range or equivalent.
  • Recoat window: Mitigation layers often have strict recoat times; missing the window can require sanding or additional prep.
  • Compatibility: Confirm the mitigation primer is approved under your chosen epoxy/urethane/polyaspartic topcoats.
  • Warranty language: Some systems require documented test results and specific installation steps to qualify.

Dew Point Control: Preventing Condensation-Driven Failures

Even if slab moisture is acceptable, condensation can sabotage adhesion. Condensation happens when the slab surface is cooler than the dew point of the air.

Beginner steps to manage dew point risk

  1. Measure: Use a thermo-hygrometer to read air temperature and relative humidity, and an infrared thermometer (or surface probe) for slab temperature.
  2. Calculate dew point: Many meters calculate it automatically; if not, use a dew point calculator.
  3. Follow a safety margin: A common practice is to keep slab temperature at least a few degrees above dew point before and during application and early cure (follow the product’s guidance).
  4. Control the environment: Run HVAC or dehumidification as needed, and avoid coating during rapid temperature drops (late afternoon/evening) when the slab can “sweat.”

When to Stop and Consult the Product Data Sheet (and Tech Support)

Moisture is one of the biggest reasons epoxy floors fail, and it is also one of the most product-specific topics. Consult the PDS (and technical support when needed) whenever:

  • Your plastic sheet test shows condensation or darkening.
  • Calcium chloride or in-situ RH results are near or above the published limits.
  • You suspect hydrostatic pressure or see recurring dampness/efflorescence.
  • You plan to coat below-grade slabs, slabs without a known vapor retarder, or areas near drains and exterior walls.
  • You are switching brands or mixing system components (primer from one line, topcoat from another).

Bring your test method, results, slab age, and site conditions (temperature, humidity, slab temperature) to the conversation. The goal is to select a system that is explicitly rated for your moisture condition, not to “hope it holds.”

Now answer the exercise about the content:

A plastic sheet test shows condensation droplets under the plastic after 24–48 hours. What is the best next step before applying an epoxy floor coating?

You are right! Congratulations, now go to the next page

You missed! Try again.

Condensation under the plastic is a strong warning of active moisture vapor movement. The plastic test doesn’t quantify it, so professional testing and possibly a moisture-mitigation system should be considered before coating.