Why hot weather changes everything
In hot weather, concrete can go from “workable” to “unfinishable” fast. Heat, direct sun, wind, and low humidity pull moisture out of the surface. That surface moisture is what keeps the top paste plastic long enough to bull float, edge, joint, and finish. When evaporation outruns bleed water (the water that rises naturally after placement), the surface dries early, stiffens, and becomes prone to cracking and weak, dusty, or flaky surfaces.
What speeds up evaporation (and shortens finishing time)
- High air temperature: warms the slab surface and the concrete, accelerating hydration and evaporation.
- Direct sun: heats the surface above air temperature; one side can dry faster than the other.
- Wind: strips away the humid boundary layer above the slab, dramatically increasing evaporation.
- Low humidity: dry air “wants” moisture; evaporation accelerates.
Practical takeaway: you can have a “hot-weather problem” even at moderate temperatures if wind and low humidity are high, or if the slab is in full sun.
Planning steps before the truck arrives (or before you open bags)
1) Choose the pour window
- Best: early morning or evening when the sun is low and the air is cooler.
- Avoid: mid-afternoon in full sun, especially with wind.
- Think ahead: finishing and early curing are part of the pour. If you start late, you may be forced to finish in peak heat or lose daylight during curing setup.
2) Shade the work area and materials
Shade reduces surface temperature and slows evaporation. Use pop-up canopies, tarps on temporary frames, or shade cloth. Keep shade high enough to allow airflow for workers but block direct sun on the slab.
- Shade forms and subgrade: hot forms and base can pull water and heat into the concrete at the edges.
- Shade staging areas: keep tools, curing supplies, and fogging equipment out of direct sun so they’re ready.
3) Stage curing water and materials (for curing, not finishing)
Have curing supplies ready before placement begins. The goal is to start curing immediately after the final finish—no scrambling for hoses or covers while the surface dries out.
- Stage water: filled sprayers, clean buckets, or a hose with a reliable nozzle for curing operations.
- Stage covers: plastic sheeting, curing blankets, or other covers you plan to use.
- Important: staged water is not for sprinkling the surface to “help finish.” Adding water to the surface during finishing weakens the top layer and can cause dusting, scaling, and delamination.
4) Cool the ingredients (small project friendly)
Lower concrete temperature buys time. Even a few degrees can noticeably extend finishing window and reduce early cracking risk.
Continue in our app.
You can listen to the audiobook with the screen off, receive a free certificate for this course, and also have access to 5,000 other free online courses.
Or continue reading below...Download the app
- Cool mixing water: use cool tap water; store jugs in shade; for bag mixes, you can chill water ahead of time.
- Shade aggregates (if you’re batching): keep sand/stone piles covered; hot aggregate can drive concrete temperature up quickly.
- Keep bags shaded: cementitious materials stored in direct sun can be hot and clumpy.
| Action | What it helps | When to do it |
|---|---|---|
| Pour in morning/evening | More finishing time, less cracking risk | Scheduling stage |
| Shade slab area | Lower surface temperature, slower evaporation | Before placement |
| Stage curing supplies | Immediate curing after final finish | Before placement |
| Cool water / shade materials | Lower concrete temperature, slower set | Before mixing/delivery |
Evaporation control during placement and finishing
Windbreaks: reduce the “drying engine”
If wind is present, set up temporary windbreaks on the windward side: tarps on stakes, plywood sheets, or construction fencing with fabric. The goal is to slow air movement across the slab surface, not create a dangerous sail. Anchor securely and keep clear of power lines.
Fogging/misting: keep the surface from drying while you work
Fogging adds a fine mist to the air above the slab to raise local humidity and slow evaporation. Done correctly, it does not leave puddles or wash the surface.
- Use a fog nozzle or pump sprayer set to a very fine mist.
- Spray upward and across the slab: aim to humidify the air, not soak the concrete.
- Timing: start as soon as the surface begins to look like it’s drying faster than expected (dulling, crusting) and continue as needed during finishing operations.
- Stop if water is visibly collecting: standing water can damage the surface and interfere with finishing.
Immediate curing after final finish (no waiting)
Hot weather is unforgiving: once the final finish is complete, begin curing immediately. The highest risk window for plastic shrinkage cracking and weak surfaces is when the surface is exposed and drying fast. Your plan should have a “handoff” from finishing to curing with minimal delay.
Practical workflow: assign one person (or your future self) to be responsible for curing setup so it happens the moment the finish is acceptable.
Mix and delivery adjustments (what to ask for and what to avoid)
Slump targets: workable, not soupy
In hot weather, it’s tempting to chase workability by adding water. Instead, aim for a slump that places and finishes well without being overly wet. Too wet increases bleeding and shrinkage; too dry can stiffen before you’re done. If you’re ordering ready-mix, discuss the placement method and finishing needs so the supplier can target an appropriate slump at discharge.
Water reducers and retarders (conceptual guidance)
Admixtures can help in hot weather:
- Water reducers: improve workability without adding extra water, helping you place and finish at a lower water content.
- Retarders: slow the set to extend finishing time when temperatures are high.
For small projects, the practical point is to plan these adjustments before the pour. If you’re using bag mix, follow manufacturer guidance and avoid improvised chemical additions unless you know the dosage and compatibility.
Avoid adding water at the surface (and why)
Sprinkling or “blessing” the slab during finishing dilutes the cement paste at the top. That creates a weak, high-water surface layer that can:
- dust or powder under foot traffic,
- flake or scale,
- delaminate (a thin layer separates from the slab),
- show color variation and blotchiness.
If the surface is drying too fast, use fogging/misting above the slab, windbreaks, shade, and faster coordination—not surface water.
Troubleshooting in the moment (and preventing it next time)
Scenario 1: Plastic shrinkage cracks appear while the concrete is still plastic
What it looks like: shallow, random cracks (often short and irregular) that show up within the first few hours, sometimes in windy/sunny conditions. They can appear even before finishing is complete.
What to do right now
- Reduce evaporation immediately: set up/adjust windbreaks, add shade, and begin fogging the air above the slab.
- Do not sprinkle water onto the surface.
- Continue finishing carefully: if the surface is still workable, you may be able to close very fine cracks during subsequent finishing passes. Avoid overworking or sealing the surface too early.
- Start curing immediately after final finish: do not delay.
Prevent recurrence
- Pour in cooler hours; add shade and windbreaks from the start.
- Have fogging ready before placement begins.
- Lower concrete temperature by cooling water/materials.
- Consider a retarder (planned in advance) if the project consistently runs out of finishing time.
Scenario 2: Crusting—top dries and stiffens while concrete underneath is still workable
What it looks like: the surface turns dull and tight, resists finishing tools, and may tear or check, while footprints or tool pressure reveals softer concrete below.
What to do right now
- Fog/mist above the slab: raise humidity to slow further crusting.
- Pause aggressive finishing: forcing a trowel into a crust can tear the surface and trap dry paste.
- Use timing and lighter passes: wait for the underlying concrete to catch up so the surface and body stiffen more uniformly.
- Keep sun and wind off: improve shade and windbreak coverage.
Prevent recurrence
- Increase shade coverage and install windbreaks before placement.
- Plan for fogging during finishing on dry/windy days.
- Ask for mix adjustments (water reducer/retarder) rather than relying on jobsite water.
Scenario 3: Rapid stiffening—concrete is getting away from you
What it looks like: the mix loses slump quickly, becomes hard to strike off and bull float, edges won’t form cleanly, and finishing windows collapse.
What to do right now
- Increase crew coordination: tighten the sequence so tasks happen without gaps (place → screed → float → edge/joint → finish).
- Reduce exposure: shade the placed concrete immediately; use windbreaks; fog the air above the slab if the surface is drying.
- Do not add water to the surface to “bring it back.”
- If you’re mixing in batches: stop making overly large batches; mix smaller amounts so each batch is placed and finished promptly.
Prevent recurrence
- Cool mixing water and keep materials shaded.
- Schedule delivery/pour for cooler hours.
- Discuss set control options (retarder) ahead of time if hot conditions are unavoidable.
- Stage tools and curing supplies so there is no downtime.
Hot-weather checklist you can use on site
Before placement: Shade ready? Windbreaks staged? Fogger/sprayer filled? Curing covers staged? Cool water available? Pour time chosen? Mix plan confirmed? During finishing: Watch for dulling/crusting. Fog air above slab as needed. Keep sun/wind off. No surface water. After final finish: Start curing immediately—no delay.