Think of the knowledge areas as everyday project concerns that show up as decisions and conversations. On the exam, questions rarely say “this is Scope Management.” Instead, they describe a situation and you infer the knowledge area from the clues: what is being decided, who is involved, what artifact is missing, and what “good” looks like in that moment.
1) Scope, Schedule, Cost: planning trade-offs
These three often appear together because they are the most visible trade-offs: what we will deliver (scope), when (schedule), and for how much (cost). Many scenarios are really about negotiating constraints and making changes without breaking commitments.
Scope Management as “what are we agreeing to deliver?”
Everyday decisions and conversations
- “Is this request part of what we agreed to deliver, or is it new?”
- “How do we define ‘done’ so everyone stops debating later?”
- “If we add this feature, what will we remove or extend?”
Key terms
- Requirements: documented needs and expectations.
- Scope statement: what is included/excluded at a high level.
- WBS (Work Breakdown Structure): deliverable-oriented decomposition of the work.
- Scope baseline: approved scope statement + WBS + WBS dictionary.
- Validation vs control: validate = customer acceptance; control = manage changes to scope baseline.
- Scope creep: unapproved expansion of scope.
What “good management” looks like
- Listen to the audio with the screen off.
- Earn a certificate upon completion.
- Over 5000 courses for you to explore!
Download the app
- Requirements are elicited, documented, prioritized, and traced to deliverables.
- Deliverables have clear acceptance criteria and an agreed acceptance process.
- The WBS is used to prevent “hidden work” and to clarify ownership.
- Change requests are handled through an agreed change control approach (not informal side agreements).
- When a change is approved, downstream impacts (schedule/cost/risk/quality) are updated, not hand-waved.
How exam questions signal Scope
- Clues: “customer says this isn’t what they wanted,” “team is building extra features,” “requirements are unclear,” “acceptance criteria missing,” “new request mid-project.”
- Artifacts mentioned or missing: requirements documentation, product backlog (adaptive), scope statement, WBS, acceptance criteria, change request.
- Typical best next step: clarify requirements/acceptance criteria, validate deliverables, or route changes through change control rather than immediately committing.
Schedule Management as “when will we finish, and what drives the date?”
Everyday decisions and conversations
- “What is the critical path and what can slip without moving the end date?”
- “Do we compress the schedule, and what risk does that add?”
- “Are dependencies real or assumed?”
Key terms
- Activities: work needed to produce deliverables.
- Dependencies: finish-to-start, start-to-start, etc.
- Network diagram: visual of activity sequencing.
- Critical path: longest path; determines project duration.
- Float/slack: allowable delay without affecting finish date.
- Milestone: significant point/event.
- Schedule baseline: approved schedule used for performance measurement.
- Crashing: add resources to shorten duration (often increases cost).
- Fast tracking: overlap activities (often increases risk/rework).
What “good management” looks like
- Activities are defined from deliverables, sequenced with explicit dependencies, and estimated realistically.
- The schedule highlights the critical path and near-critical paths (where small slips become big problems).
- Progress is tracked against the schedule baseline; variances trigger analysis, not blame.
- Schedule compression is used intentionally (crash/fast track) with documented trade-offs and risk responses.
Practical step-by-step: responding to a schedule slip
- Confirm the facts: what activity slipped, by how much, and why.
- Check criticality: is it on the critical path or consuming float?
- Identify options: re-sequence, remove constraints, crash, fast track, reduce scope, or extend date.
- Evaluate impacts: cost, risk, quality, resource availability, stakeholder expectations.
- Decide and update: adjust schedule, communicate changes, and update related plans/baselines as required.
How exam questions signal Schedule
- Clues: “behind schedule,” “missed milestone,” “dependency,” “critical path,” “resource availability affecting dates,” “what should PM do to shorten timeline?”
- Look for compression language: “overlap,” “add people,” “work overtime,” “parallel work.”
- Best answer often includes analyzing critical path/float before taking action.
Cost Management as “what will it cost, and are we staying within the budget?”
Everyday decisions and conversations
- “Can we afford this change?”
- “Are we burning money faster than planned?”
- “Do we need more contingency, or is this poor estimating?”
Key terms
- Estimate: expected cost of work.
- Budget: time-phased allocation of costs.
- Cost baseline: approved version of the budget used to measure performance.
- Contingency reserve: for known-unknowns (identified risks).
- Management reserve: for unknown-unknowns (not in baseline).
- EVM basics: PV (planned value), EV (earned value), AC (actual cost), CPI (cost performance index), SPI (schedule performance index).
What “good management” looks like
- Costs are estimated at an appropriate level of detail and rolled up into a budget.
- Spending is tracked; variances trigger root-cause analysis and corrective action.
- Reserves are understood and used correctly (contingency vs management).
- Forecasting is updated when conditions change, not only at the end.
Practical step-by-step: handling a cost overrun signal
- Verify the variance: compare AC vs planned and confirm accounting timing.
- Assess performance: use CPI/EV where applicable to see if it’s a trend.
- Find the driver: scope change, estimation error, productivity issues, vendor rates, rework.
- Choose response: corrective action, re-estimate, use contingency (if risk-related), or submit change request if baseline must change.
- Communicate: explain impacts and options in stakeholder language (not just numbers).
How exam questions signal Cost
- Clues: “over budget,” “cost variance,” “burn rate,” “funding limit,” “reserve,” “EVM metrics,” “forecast at completion.”
- Best answers often involve analyzing variance and using the correct reserve/change control path rather than immediately requesting more money.
2) Quality and Resources: capability and performance
Quality and Resources show up when the project struggles to produce results reliably: defects, rework, low productivity, skill gaps, burnout, or unclear roles. These areas are about building the capability to deliver and sustaining performance.
Quality Management as “how do we prevent defects and prove the work meets expectations?”
Everyday decisions and conversations
- “What does ‘high quality’ mean here—what are the acceptance criteria?”
- “Are we inspecting quality in at the end, or building it in?”
- “Why are we seeing repeated defects?”
Key terms
- Quality vs grade: quality = meets requirements; grade = category/feature set.
- Prevention vs inspection: prevent defects vs detect defects.
- Cost of quality: prevention/appraisal vs failure costs.
- Quality assurance (process-focused) vs quality control (deliverable-focused).
- Continuous improvement: retrospectives/lessons learned used to improve process.
- Common tools: cause-and-effect diagram, control charts, Pareto chart, checklists.
What “good management” looks like
- Quality requirements and acceptance criteria are explicit and testable.
- Processes are designed to prevent defects (peer reviews, automation, standards).
- Quality metrics are monitored; trends trigger improvement actions.
- When defects occur, the team addresses root causes, not just symptoms.
Practical step-by-step: repeated defects in deliverables
- Confirm the defect pattern: what types, where found, frequency.
- Check acceptance criteria: are they clear and agreed?
- Do root-cause analysis: use a fishbone/5 Whys; look for process gaps.
- Implement prevention: update standards, add reviews, improve test coverage, train team.
- Measure improvement: track defect rate and rework time over iterations/releases.
How exam questions signal Quality
- Clues: “defects,” “rework,” “customer complaints,” “acceptance testing,” “process improvement,” “control chart out of control,” “audit.”
- Best answers often emphasize prevention and process improvement over “inspect more at the end.”
Resource Management as “do we have the right people and tools, and are they set up to perform?”
Everyday decisions and conversations
- “Who is accountable for this deliverable?”
- “We’re overloaded—what gets deprioritized?”
- “We need a specialist—do we train, hire, or contract?”
Key terms
- Resource planning: identifying and acquiring needed resources.
- Roles and responsibilities: who does what; often clarified with a RACI.
- Team development: training, coaching, team norms.
- Conflict management: addressing disagreements constructively.
- Motivation and performance: feedback, recognition, removing blockers.
- Resource calendars: availability constraints.
What “good management” looks like
- Roles are clear; handoffs and ownership are not ambiguous.
- Capacity and availability are realistic; plans reflect constraints.
- PM removes impediments and resolves conflicts early.
- Skills gaps are addressed through training, mentoring, or procurement.
- Work is balanced to avoid chronic overtime and burnout.
Practical step-by-step: resolving a role/ownership conflict
- Clarify the deliverable: what outcome is needed and by when.
- Map responsibilities: draft a RACI for the affected work.
- Facilitate agreement: align functional managers/team leads on ownership and decision rights.
- Document and communicate: publish the agreed roles and escalation path.
- Monitor: watch for repeated confusion and adjust.
How exam questions signal Resources
- Clues: “resource shortage,” “team conflict,” “low morale,” “skills gap,” “functional manager,” “matrix organization,” “availability,” “overtime.”
- Best answers often involve clarifying roles, negotiating for resources, developing the team, or removing impediments rather than simply “work harder.”
3) Communications and Stakeholder: alignment and expectations
Many project problems are not technical—they are expectation problems. Communications and Stakeholder Management focus on who needs what information, when, in what format, and how you keep people engaged and supportive.
Communications Management as “how information moves so work stays coordinated”
Everyday decisions and conversations
- “Who needs to know this decision, and how quickly?”
- “Are we communicating too much noise or too little clarity?”
- “What is the escalation path when issues arise?”
Key terms
- Communication requirements analysis: identifying information needs of stakeholders.
- Communication methods: interactive, push, pull.
- Communication plan: what, when, who, how, and owner.
- Information radiators: visible status (dashboards, boards) that reduce confusion.
- Feedback loop: confirmation that message was understood.
What “good management” looks like
- Communication is intentional: tailored to audience and decision needs.
- Status reporting is consistent, honest, and decision-oriented (issues, impacts, options).
- Escalations happen early with context and recommendations.
- Meetings have purpose, agenda, and outcomes; decisions are documented.
Practical step-by-step: building a simple communication plan
- List audiences: sponsor, customer, team, vendors, operations, regulators (as applicable).
- Define information needs: decisions they make, risks they care about, level of detail.
- Select method and cadence: weekly steering update, daily team sync, monthly release notes, etc.
- Assign owners: who prepares, who approves, who sends.
- Confirm understanding: incorporate feedback and adjust.
How exam questions signal Communications
- Clues: “misunderstanding,” “people surprised,” “no one informed,” “status unclear,” “wrong audience,” “communication breakdown,” “escalation.”
- Best answers often include updating the communication plan, choosing the right method (interactive vs push vs pull), and ensuring feedback/confirmation.
Stakeholder Management as “who can affect the project, and how do we keep them engaged?”
Everyday decisions and conversations
- “Who is resisting this change, and why?”
- “Who has influence but isn’t in the meetings?”
- “What does success look like for each stakeholder group?”
Key terms
- Stakeholder identification: recognizing people/groups impacted or influential.
- Stakeholder analysis: interest, influence, impact, attitude.
- Engagement assessment: current vs desired engagement levels.
- Stakeholder engagement plan: strategies to involve and manage expectations.
What “good management” looks like
- Stakeholders are identified early and revisited as the project evolves.
- Engagement is proactive: you address concerns before they become blockers.
- Expectations are negotiated and documented; changes are managed transparently.
- Resistance is treated as information (needs, fears, incentives), not as “difficult people.”
Practical step-by-step: dealing with a powerful resistant stakeholder
- Diagnose the resistance: what are they protecting (budget, reputation, workload, control)?
- Meet 1:1: listen, clarify impacts, and ask what would make it acceptable.
- Adjust engagement strategy: involve them in decisions, provide targeted updates, address their success criteria.
- Align with sponsor if needed: when authority is required to resolve priority conflicts.
- Track engagement: confirm attitude shifts and follow through on commitments.
How exam questions signal Stakeholders
- Clues: “stakeholder unhappy,” “resistance,” “new stakeholder appears,” “influence,” “politics,” “sponsor concern,” “users not adopting.”
- Best answers often focus on analyzing stakeholder needs and updating the engagement plan rather than only sending more status emails.
4) Risk and Procurement: uncertainty and external dependency
Risk and Procurement often appear when the project depends on things outside the team’s direct control: uncertain events, vendor performance, contracts, lead times, and compliance constraints.
Risk Management as “what could happen, and what will we do about it?”
Everyday decisions and conversations
- “What could derail us, and how early would we see it?”
- “Which risks deserve budget/time now vs later?”
- “Are we accepting this risk knowingly or accidentally?”
Key terms
- Risk: uncertain event/condition that can affect objectives.
- Threats vs opportunities: negative vs positive risks.
- Risk register: identified risks, owners, responses, triggers.
- Qualitative analysis: probability/impact prioritization.
- Quantitative analysis: numerical impact (e.g., simulation) when warranted.
- Responses (threats): avoid, mitigate, transfer, accept.
- Responses (opportunities): exploit, enhance, share, accept.
- Contingency plan and fallback plan: planned actions if risk occurs / if primary response fails.
- Risk owner: person accountable for monitoring and response execution.
What “good management” looks like
- Risks are identified continuously, not only at kickoff.
- High-priority risks have owners, triggers, and funded responses.
- Risk discussions are integrated into planning and status (not a separate ritual).
- When a risk becomes an issue, the team executes the planned response quickly.
Practical step-by-step: turning a vague worry into a managed risk
- Write it as an event: “If X happens, then Y impact occurs.”
- Estimate probability and impact: use agreed scales.
- Choose a response: avoid/mitigate/transfer/accept (or opportunity strategies).
- Assign an owner: someone who can act.
- Define triggers: early warning indicators.
- Plan contingency: time/cost set aside and actions to take.
How exam questions signal Risk
- Clues: “uncertainty,” “what if,” “potential,” “probability,” “impact,” “contingency,” “risk response,” “risk register,” “trigger.”
- Best answers often include updating the risk register, assigning an owner, and selecting an appropriate response rather than reacting ad hoc.
Procurement Management as “how we buy, manage, and integrate external work”
Everyday decisions and conversations
- “Should we build this in-house or buy it?”
- “What contract type fits the uncertainty?”
- “Vendor is late—what are our options under the contract?”
Key terms
- Make-or-buy analysis: deciding internal vs external sourcing.
- RFP/RFQ: request for proposal/quotation.
- SOW: statement of work (what the vendor will deliver).
- Contract types: fixed-price, cost-reimbursable, time & materials.
- Source selection criteria: how bids are evaluated.
- Procurement documents: contracts, change orders, acceptance records.
- Claims: disputes requiring resolution per contract terms.
What “good management” looks like
- Procurement approach matches uncertainty: more defined scope supports fixed-price; high uncertainty may require T&M or cost-reimbursable with controls.
- SOW and acceptance criteria are clear to prevent scope disputes.
- Vendor performance is monitored with agreed metrics and regular reviews.
- Changes go through formal contract change control, not informal requests.
- PM coordinates with legal/procurement functions and follows organizational policies.
Practical step-by-step: selecting a contract type (exam-friendly logic)
- Assess scope clarity: well-defined vs evolving.
- Assess risk tolerance: who should carry cost risk—buyer or seller?
- Match contract: fixed-price for stable scope; T&M for short-term/uncertain effort; cost-reimbursable when scope is uncertain but buyer can manage oversight.
- Define acceptance and change process: how deliverables are approved and how changes are priced.
- Plan vendor management: cadence, reporting, escalation, and performance measures.
How exam questions signal Procurement
- Clues: “vendor,” “contract,” “bid,” “RFP,” “procurement department,” “claims,” “SOW,” “outsourcing,” “make-or-buy.”
- Best answers often reference contract terms, formal change control, and working through procurement processes rather than negotiating side deals directly with the seller.
5) Integration: coordination and decision authority
Integration is the PM’s “connective tissue” work: coordinating across knowledge areas, ensuring decisions are consistent, and maintaining a single coherent plan. Many exam questions are Integration questions disguised as something else because they involve trade-offs, change control, and aligning the whole project.
Integration Management as “how the project stays one project”
Everyday decisions and conversations
- “If we approve this change, what else must change (schedule, cost, risk, quality)?”
- “Who has authority to approve this, and what is the escalation path?”
- “How do we keep teams working toward the same objectives?”
Key terms
- Project management plan: integrated set of subsidiary plans and baselines.
- Benefits management plan: how expected benefits will be realized (when applicable).
- Change control: formal evaluation/approval of changes.
- CCB (Change Control Board): group that reviews/approves changes (when used).
- Configuration management: controlling versions of deliverables and documents.
- Lessons learned register: captured insights during the project.
- Issue log: current problems requiring resolution (not uncertain risks).
What “good management” looks like
- There is a single source of truth for baselines and approved changes.
- Trade-offs are made transparently with the right decision-makers.
- Impacts are assessed across scope/schedule/cost/quality/risk/resources before committing.
- Issues are tracked, owned, and resolved with clear escalation.
- Teams and stakeholders understand decision authority and governance.
Practical step-by-step: handling a proposed change request end-to-end
- Capture the change: document the request and rationale.
- Analyze impacts: scope, schedule, cost, quality, risk, resources, procurement/contract implications.
- Identify options: approve as-is, reject, defer, or approve with trade-offs (reduce scope elsewhere, extend date, add budget).
- Route for approval: follow the defined authority (PM, sponsor, CCB, product owner, etc.).
- Update artifacts: baselines, plans, backlog, contracts, and communications as needed.
- Communicate decision: who needs to know, what changes, effective date, and next steps.
How exam questions signal Integration
- Clues: “what should the PM do next?” with multiple areas impacted; “change request,” “baseline updates,” “conflicting priorities,” “governance,” “project management plan,” “CCB.”
- Integration often appears when the correct answer is about coordinating, assessing impacts, and following change control rather than jumping straight into execution.
Quick clue map: spotting the knowledge area from question language
| Knowledge area | Common clues in scenarios | Typical PM move |
|---|---|---|
| Scope | Requirements unclear, acceptance dispute, extra features, “not what we asked for” | Clarify requirements/acceptance; manage changes formally |
| Schedule | Milestones missed, dependencies, critical path, compression requests | Analyze critical path/float; choose compression/trade-offs |
| Cost | Over budget, reserves, funding limits, EVM metrics | Analyze variance; forecast; use correct reserve/change control |
| Quality | Defects, rework, audits, control charts, process issues | Root-cause analysis; prevention; improve process and criteria |
| Resources | Skill gaps, role confusion, conflict, low morale, availability constraints | Clarify roles; negotiate resources; develop team; remove blockers |
| Communications | Misunderstanding, wrong audience, surprises, unclear status | Tailor communication method/cadence; confirm understanding |
| Stakeholder | Resistance, influence/power dynamics, adoption issues, new stakeholders | Analyze engagement; adjust strategy; manage expectations |
| Risk | Uncertainty, “what if,” probability/impact, triggers, contingency | Update risk register; assign owner; plan/execute responses |
| Procurement | Vendors, contracts, RFP/SOW, claims, outsourcing | Follow procurement/contract terms; manage vendor performance |
| Integration | Cross-area impacts, change control, governance, “PM do next?” | Assess impacts; coordinate decisions; update plans/baselines |